Jul 12, 2025
Downtown Streetscape Improvement
Walkability audit
Field review of sidewalks, ramps, and crossings.
Complete
2026
May 18, 2026
Riverfront Park Redesign
Flood and site study
Complete
May 28, 2026
Downtown Streetscape Improvement
Concept alternatives
Two streetscape characters presented to the public.
Complete
Jun 17, 2026
Main Street Safety Improvements
Crash analysis
Complete
Jul 7, 2026
Community Recreation Center
Needs assessment
Complete
Aug 1, 2026
2027 City Budget
Resident survey opens
Now
Aug 16, 2026
Comprehensive Plan Update
Listening sessions
Now
Aug 16, 2026
Main Street Safety Improvements
Map comments
Now
Aug 16, 2026
Riverfront Park Redesign
Idea collection
Now
Aug 27, 2026
Downtown Streetscape Improvement
Public survey and open house
Choose lighting, trees, and crossing locations.
Now
Sep 9, 2026
2027 City Budget
Budget hearing
Upcoming
Sep 15, 2026
Community Recreation Center
Site and program engagement
Upcoming
Sep 30, 2026
Downtown Streetscape Improvement
Council concept selection
Staff recommendation based on resident feedback.
Upcoming
Oct 25, 2026
2027 City Budget
Council first reading
Upcoming
Oct 25, 2026
Riverfront Park Redesign
Draft master plan
Upcoming
Dec 14, 2026
Downtown Streetscape Improvement
Detailed design
Upcoming
2027
Feb 12, 2027
Comprehensive Plan Update
Draft plan
Upcoming
May 23, 2027
Downtown Streetscape Improvement
Construction
Phased by block to keep businesses open.
Upcoming