A new park along the Great Miami River with trails, play, gathering space, and restored river edge.
Comments
Public discussion
No account needed. Comments are public and visible on this page as soon as you post.
No comments yet. Be the first to add one.
Timeline
Where this project stands
May 18, 2026
Flood and site study
Complete
Aug 16, 2026
Idea collection
Now
Oct 25, 2026
Draft master plan
Upcoming
Closed loop
You said. We did.
You said
71% supported relocating parking
71% supported moving parking inland if trail access and a drop-off were kept.
We did
Parking will move to the existing overflow field. A 10-minute drop-off remains at the trailhead.
Why. The flood study found the current lot is in the floodway. Relocating it is required for restoration funding and reduces closures after high water.
Quick poll
If Riverfront Park could do one thing exceptionally well, what should it be?
You can choose one. Results are visible as you vote.
Idea board
What should this include?
A fishing platform that kids can use
Maya ThompsonRiver access
A low, safe platform with railings so grandparents can fish with kids without standing on the muddy bank.
Shade sails over the playground
Luis OrtegaPlay
The current playground has almost no shade after 11 a.m. Sails or a grove of trees would make summer usable.
A quiet loop for walking meetings
Ruth NguyenTrails
A 1/4-mile smooth loop with benches, separate from the playground noise, for older adults.
City response. This is consistent with the trail connection goal. We will include a measured loop in the draft plan.
Keep the view of the water from the lawn
Chris PatelDesign
Please do not plant a solid hedge along the river. The open view is why people come.
Restrooms that are actually open
AnonymousFacilities
Portable toilets are not enough for a park this size. Year-round restrooms matter as much as the playground.
Location
Riverfront Park
800 River Road, Franklin, OH
Questions
Ask the project team
Meetings
Riverfront Park design drop-in
Thu, Aug 20, 2026, 10:00 AM · Riverfront Park trailhead, 800 River Road
Updates
August 4, 2026 · Priya Nair
Riverbank parking will move inland
The flood study is complete. The existing 60-space lot along the river will be relocated. That decision is not being revisited; we are now asking how to use the recovered river edge.
Documents
Riverfront flood and site study
Floodway, parking, and restoration constraints.
FAQs
Will the playground close?
The existing playground will remain until a replacement is funded and built. We will not leave a gap without play equipment.
Gallery



Project team
Priya NairParks director- Chris LangLandscape architect
Budget
$6,800,000
Parks levy, Clean Ohio, and private donations